Force Majeure and the Doctrine of Impossibility
The COVID-19 pandemic is resulting in landlords and tenants closely reviewing a clause in their lease that was long considered unimportant boilerplate. Yes, we are referring to the "force majeure" provision.
April 02, 2020 at 03:53 PM
8 minute read
The COVID-19 pandemic is resulting in landlords and tenants closely reviewing a clause in their lease that was long considered unimportant boilerplate. Yes, we are referring to the "force majeure" provision. "Force majeure" is translated from French as "superior strength" and is often thought of an act of God or act of nature. Black's law dictionary defines it as "a contractual provision allocating the risk of loss if performance becomes impossible or impracticable, especially as a result of an event or effect that the parties could not have anticipated or controlled." In the coming months many conversations will take place regarding the applicability of the force majeure clause to closures related to the COVID-19 pandemic as well as the related doctrine of impossibility.
A force majeure event is an act that is unforeseen and beyond the reasonable control of the landlord and tenant. Because of the force majeure event, depending on the language in the lease, the parties might be excused from some (but perhaps not all) of the obligations under the agreement. An example could be a storm such as a major hurricane, an earthquake or an act of terrorism. Sometimes the clauses include labor shortages or issues or inability to procure materials, but financial inability is usually excluded. And importantly, rent is usually excluded from the type of obligations that are excused. Force majeure provisions are usually (but not always) pro-landlord and not heavily negotiated. Think of them as the boilerplate that is usually ignored except in large deals where the tenant has more leverage. The language may or may not include pandemics or public health emergencies as an excusable event. A good negotiator might try to include issues relating to failures to obtain building permits.
Two examples of longer force majeure clause in an office lease are as follows:
Example #1
In the event that the Landlord or the Tenant will be unable to fulfill, or shall be delayed or prevented from the fulfillment of, any obligation in this Lease by reason of municipal delays in providing necessary approvals or permits, the other party's delay in providing approvals as required in this Lease, strikes, third party lockouts, fire, flood, earthquake, lightning, storm, acts of God, war, riots, insurrections or other reasons of like nature beyond the reasonable control of the party delayed or prevented from fulfilling any obligation in this Lease (excepting any delay or prevention from such fulfillment caused by a lack of funds or other financial reasons) and provided that such party uses all reasonable diligence to overcome such unavoidable delay, then the time period for performance of such an obligation will be extended for a period equivalent to the duration of such unavoidable delay. Municipal delays in providing necessary approvals or permits, the other party's delay in providing approvals as required in this Lease, strikes, third party lockouts, fire, flood, earthquake, lightning, storm, acts of God, war, riots, insurrections or other reasons of like nature beyond the reasonable control of the party delayed or prevented from fulfilling any obligation in this Lease (excepting any delay or prevention from such fulfillment caused by a lack of funds or other financial reasons) and provided that such party uses all reasonable diligence to overcome such unavoidable delay, then the time period for performance of such an obligation will be extended for a period equivalent to the duration of such unavoidable delay
Example #2
Any prevention, delay or stoppage due to strikes, lockouts, labor disputes, acts of God, inability to obtain services, labor, or materials or reasonable substitutes therefor, governmental actions, civil commotions, fire or other casualty, and other causes beyond the reasonable control of the party obligated to perform, except with respect to the obligations imposed with regard to Rent and other charges to be paid by Tenant pursuant to this Lease (collectively, a "Force Majeure Event"), notwithstanding anything to the contrary contained in this Lease, shall excuse the performance of such party for a period equal to any such prevention, delay or stoppage and, therefore, if this Lease specifies a time period for performance of an obligation of either party, that time period shall be extended by the period of any delay in such party's performance caused by a Force Majeure Event. Either party shall provide prompt notice of any Force Majeure Event to the other party herein.
As you can see, a pandemic is not expressly included in either of the sample provisions even in these longer provisions, and only the second example expressly carves out rent as an obligation that is forgiven. That said, more likely than not, the force majeure provisions in a sophisticated lease will expressly exclude rental obligations from the types of obligations for which a tenant can be excused because of truly unforeseen events outside of their control.
It is critical to closely review the language, but local state courts typically enforce the clear and unambiguous terms of a contract. And note that the courts will place the burden of establishing the conditions of force majeure on the party raising the provision to excuse an otherwise required obligation. Therefore, as a matter of a law, the exclusion of rent from the force majeure clause if it is expressly included in such a provision may effectively prevent the tenant from avoiding that obligation under the lease.
|Doctrine of Impossibility
Most leases will contain a force majeure clause somewhere in the boilerplate, but for agreements that do not contain such a clause (and arguably, as will be discussed below, even with leases that have such a clause), the tenant might instead raise the doctrine of impossibility. Depending on the specific law of the applicable state, the party relying on the defense must typically establish: 1) the unexpected occurrence of an intervening act; 2) such occurrence was of such a character that its non-occurrence was a basic assumption of the agreement of the parties; and 3) that occurrence made performance impracticable. A critical factor is whether the party agreed in the lease to assume the risk of performance, whether possible or not.
For example, a restaurant or bar tenant with a narrowly defined permitted use clause might have a strong argument to use the doctrine of impossibility if their business was shut down by order of the governor. The defense if successful would act to excuse performance by the party if an event occurs whose non-occurrence was a basic assumption of the agreement and if it makes performance impossible or impractical. The precise language in the lease is critically important as well as the circumstances of why the tenant could not operate.
Normally the courts will defer to the language in the agreement and a force majeure clause will control over this doctrine of impossibility. So if the language of the lease effectively requires that the tenant accept the risk of paying rent even in the time of a force majeure event, a court might hold that the tenant accepted the risk of paying rent even when an impossibility event occurred. Though the landlord's argument likely becomes more difficult when the government rules that the only use permitted under the lease is no longer allowed. Note further, however, that there is case law where the doctrine of impossibility trumps the force majeure clause, but this is usually in the context of a contract for commercial goods. Given the unprecedented nature of this pandemic and the resulting closures, it is not difficult to see courts taking creative approaches so landlords and tenants need to be prepared for all arguments.
Once we are past the current crisis, it would be prudent for all parties to update their form leases to expressly include pandemics and epidemics as force majeure events, make clear whether the obligation to pay rent is excused or not, and require the parties to deliver notice of force majeure within a certain period of days after the start of the delay period.
*****
John G. Kelly is a partner with Bean Kinney & Korman PC and a member of Commercial Leasing Law & Strategy's Board of Editors. His practice focuses on commercial leasing and he represents national landlords and tenants. Please contact him at [email protected] should you have any questions or need assistance.
This content has been archived. It is available through our partners, LexisNexis® and Bloomberg Law.
To view this content, please continue to their sites.
Not a Lexis Subscriber?
Subscribe Now
Not a Bloomberg Law Subscriber?
Subscribe Now
NOT FOR REPRINT
© 2024 ALM Global, LLC, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more information visit Asset & Logo Licensing.
You Might Like
View AllFrom ‘Deep Sadness’ to Little Concern, Gaetz’s Nomination Draws Sharp Reaction From Lawyers
7 minute read‘What’s Up With Morgan & Morgan?’ Law, Advertising and a Calculated Rise
10 minute readConservative Boutiques That Backed Trump Reap Their Rewards
What Will Happen to the Nominees in Florida's Southern and Middle Districts?
3 minute readLaw Firms Mentioned
Trending Stories
- 1The State of Cost Recovery — Post COVID
- 2Why Is It Becoming More Difficult for Businesses to Mandate Arbitration of Employment Disputes?
- 3The Whys and Hows of a Mediator’s Proposal
- 4Litigators of the Week: A Trade Secret Win at the ITC for Viking Over Promising Potential Liver Drug
- 5Litigator of the Week Runners-Up and Shout-Outs
Who Got The Work
Michael G. Bongiorno, Andrew Scott Dulberg and Elizabeth E. Driscoll from Wilmer Cutler Pickering Hale and Dorr have stepped in to represent Symbotic Inc., an A.I.-enabled technology platform that focuses on increasing supply chain efficiency, and other defendants in a pending shareholder derivative lawsuit. The case, filed Oct. 2 in Massachusetts District Court by the Brown Law Firm on behalf of Stephen Austen, accuses certain officers and directors of misleading investors in regard to Symbotic's potential for margin growth by failing to disclose that the company was not equipped to timely deploy its systems or manage expenses through project delays. The case, assigned to U.S. District Judge Nathaniel M. Gorton, is 1:24-cv-12522, Austen v. Cohen et al.
Who Got The Work
Edmund Polubinski and Marie Killmond of Davis Polk & Wardwell have entered appearances for data platform software development company MongoDB and other defendants in a pending shareholder derivative lawsuit. The action, filed Oct. 7 in New York Southern District Court by the Brown Law Firm, accuses the company's directors and/or officers of falsely expressing confidence in the company’s restructuring of its sales incentive plan and downplaying the severity of decreases in its upfront commitments. The case is 1:24-cv-07594, Roy v. Ittycheria et al.
Who Got The Work
Amy O. Bruchs and Kurt F. Ellison of Michael Best & Friedrich have entered appearances for Epic Systems Corp. in a pending employment discrimination lawsuit. The suit was filed Sept. 7 in Wisconsin Western District Court by Levine Eisberner LLC and Siri & Glimstad on behalf of a project manager who claims that he was wrongfully terminated after applying for a religious exemption to the defendant's COVID-19 vaccine mandate. The case, assigned to U.S. Magistrate Judge Anita Marie Boor, is 3:24-cv-00630, Secker, Nathan v. Epic Systems Corporation.
Who Got The Work
David X. Sullivan, Thomas J. Finn and Gregory A. Hall from McCarter & English have entered appearances for Sunrun Installation Services in a pending civil rights lawsuit. The complaint was filed Sept. 4 in Connecticut District Court by attorney Robert M. Berke on behalf of former employee George Edward Steins, who was arrested and charged with employing an unregistered home improvement salesperson. The complaint alleges that had Sunrun informed the Connecticut Department of Consumer Protection that the plaintiff's employment had ended in 2017 and that he no longer held Sunrun's home improvement contractor license, he would not have been hit with charges, which were dismissed in May 2024. The case, assigned to U.S. District Judge Jeffrey A. Meyer, is 3:24-cv-01423, Steins v. Sunrun, Inc. et al.
Who Got The Work
Greenberg Traurig shareholder Joshua L. Raskin has entered an appearance for boohoo.com UK Ltd. in a pending patent infringement lawsuit. The suit, filed Sept. 3 in Texas Eastern District Court by Rozier Hardt McDonough on behalf of Alto Dynamics, asserts five patents related to an online shopping platform. The case, assigned to U.S. District Judge Rodney Gilstrap, is 2:24-cv-00719, Alto Dynamics, LLC v. boohoo.com UK Limited.
Featured Firms
Law Offices of Gary Martin Hays & Associates, P.C.
(470) 294-1674
Law Offices of Mark E. Salomone
(857) 444-6468
Smith & Hassler
(713) 739-1250