South Florida Builders Active, But Pipeline Stalls Amid Coronavirus
South Florida public agencies have canceled zoning and commission meetings where action on proposed developments was pending, but construction, permitting and inspections continue.
March 19, 2020 at 03:48 PM
6 minute read
Real estate construction is active across South Florida despite other industry shutdowns in the coronavirus pandemic, but projects in the pre-approval stage are at a standstill.
Governments agencies have canceled zoning and commission meetings for at least the next month to abide by the social distancing recommendations to avoid infection.
It's necessary and justified but with far-reaching implications, attorney Javier Vazquez said.
"The biggest issue as far as delays go is with zoning hearing applications because of the fact that they rightfully are getting canceled. Every time you have a rescheduling of a public hearing, it requires re-advertisement, it causes a considerable delay to the project," said Vazquez, partner at Berger Singerman and member of the government and regulatory practice in Miami. "Permitting and construction can't commit typically until these entitlements are in place, so it kind of has a domino effect on the design line for the proposed development and the construction."
The Miami Planning, Zoning and Appeals Board didn't meet Wednesday and canceled its April 1 meeting. In Miami Beach, the Design Review Board meeting set for April 7 was canceled, and the Land Use and Sustainability Committee meeting scheduled April 14 was postponed a week.
Construction work in still underway, unlike places like the Massachusetts cities of Boston and Cambridge, which halted work.
Art Falcone, whose Miami Worldcenter in downtown Miami and Plantation Walk near Fort Lauderdale are chugging along, said at least crews generally don't work close to one another.
"The question is going to be if there's any mandates from local governments," said Falcone, who is a partner in Worldcenter and the Plantation Walk master developer. "Obviously, we will comply with all state and federal and local mandates."
He wondered aloud if he could foresee extra costs and noted construction sites require services ranging from portable toilets to dumpsters and cranes.
"Your job is delayed by a month, you still have $1,000 a day for the crane," Falcone said.
Attorney Gary Stein agreed any work interruption would add to costs.
"In the construction industry, time is money. So if there is a suspension of a project or any delay in the construction of a project, there is going to be some cost impact," said Stein, Peckar & Abramson Miami co-managing partner.
He represents general contractors and construction managers working on more than 30 projects across the region. He suggests his clients should examine their agreements with developers to understand their rights and keep records of accrued costs in case of a work halt, he said.
Force Majeure
Developers retain general contractors under agreements with force majeure clauses, which addresses unmet obligations over uncontrollable circumstances referred to as "acts of God." In South Florida, these generally have been applied in South Florida to hurricanes.
Coronavirus has prompted questions about whether pandemic-related delays are covered under force majeure, and the answer depends, Carlton Fields Atlanta shareholder Daniel Weede wrote on the firm's website.
A broad force majeure clause might not specify a pandemic, but it wouldn't exclude it either, Weede wrote. A more specific definition would limit force majeure to specific events.
Contracts also might have project suspension and termination clauses, Stein noted.
"You have to look at the clauses and their situations to see what they provide in terms of rights to contractors for time extension and additional compensation if and when the project has restarted," he said.
Permits, Inspections
Projects might face hurdles if county and municipal building departments cease issuing permits and performing inspections.
Miami Beach is operating as usual, a spokeswoman said.
Miami is doing all building permit-related services via email, including requests for revisions, phase and completion permits; changes of contractors, architects and engineers; new contractor registrations; and requests for project fee waivers, according to a news release.
Boca Raton is performing inspections and processing building permit requests, including new applications, online. City staff members are working remotely to help with building permits as the building department building was closed.
But the experts are considering what might happen if the pace of construction slows.
"In the short period of time, the impact would be minimal. It all depends on how long those building departments stop accepting new building permits. For a short period of time, it would be a hiccup but it's something the system can definitely adapt to," said Peter Dyga, president and CEO of the East Coast chapter of the Associated Builders and Contractors Florida .
Inspections are done throughout construction and when a project is ready for an occupancy certificate, said Greg Main-Baillie, Colliers International executive managing director of the Florida development services group in Boca Raton.
Also of note is that if coronavirus delays projects, developers won't get a break if their development orders and building permits approved by municipalities expire.
The Legislature in 2019 revised state law that previously allowed development orders and building permits to be extended when the governor declares a state of emergency. Many developers got extensions in years past for the Zika virus outbreak and opioid crisis.
"Unfortunately, the current health crisis caused by the Coronavirus does not appear to fall under this definition currently," wrote Adler, based in Miami.
Still, there are some reprieves on a case-by-case basis as Miami Beach provided a one-month extensions for permits expiring from the past month through April 16.
"Hopefully, state legislation will be forthcoming to extend development orders and building permits in response to the COVID-19 state of emergency that has already caused statewide impacts and business closures," Adler added.
With other places ordering a construction moratorium, the subject is open for discussion.
"I can't say with a degree of certainty," Stein said. "We are just going to have to see what happens over the next days and weeks in terms of the local authorities taking similar action. It's certainly in the realm of possibilities."
NOT FOR REPRINT
© 2024 ALM Global, LLC, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more information visit Asset & Logo Licensing.
You Might Like
View AllFowler White Burnett Opens Jacksonville Office Focused on Transportation Practice
3 minute readHow Much Coverage Do You Really Have? Valuation and Loss Settlement Provisions in Commercial Property Policies
10 minute readThe Importance of 'Speaking Up' Regarding Lease Renewal Deadlines for Commercial Tenants and Landlords
6 minute readMeet the Attorneys—and Little Known Law—Behind $20M Miami Dispute
Law Firms Mentioned
Trending Stories
- 1'Fulfilled Her Purpose on the Court': Presiding Judge M. Yvette Miller Is 'Ready for a New Challenge'
- 2Litigation Leaders: Greenspoon Marder’s Beth-Ann Krimsky on What Makes Her Team ‘Prepared, Compassionate and Wicked Smart’
- 3A Look Back at High-Profile Hires in Big Law From Federal Government
- 4Grabbing Market Share From Rivals, Law Firms Ramped Up Group Lateral Hires
- 5Navigating Twitter's 'Rocky Deal Process' Helped Drive Simpson Thacher's Tech and Telecom Practice
Who Got The Work
Michael G. Bongiorno, Andrew Scott Dulberg and Elizabeth E. Driscoll from Wilmer Cutler Pickering Hale and Dorr have stepped in to represent Symbotic Inc., an A.I.-enabled technology platform that focuses on increasing supply chain efficiency, and other defendants in a pending shareholder derivative lawsuit. The case, filed Oct. 2 in Massachusetts District Court by the Brown Law Firm on behalf of Stephen Austen, accuses certain officers and directors of misleading investors in regard to Symbotic's potential for margin growth by failing to disclose that the company was not equipped to timely deploy its systems or manage expenses through project delays. The case, assigned to U.S. District Judge Nathaniel M. Gorton, is 1:24-cv-12522, Austen v. Cohen et al.
Who Got The Work
Edmund Polubinski and Marie Killmond of Davis Polk & Wardwell have entered appearances for data platform software development company MongoDB and other defendants in a pending shareholder derivative lawsuit. The action, filed Oct. 7 in New York Southern District Court by the Brown Law Firm, accuses the company's directors and/or officers of falsely expressing confidence in the company’s restructuring of its sales incentive plan and downplaying the severity of decreases in its upfront commitments. The case is 1:24-cv-07594, Roy v. Ittycheria et al.
Who Got The Work
Amy O. Bruchs and Kurt F. Ellison of Michael Best & Friedrich have entered appearances for Epic Systems Corp. in a pending employment discrimination lawsuit. The suit was filed Sept. 7 in Wisconsin Western District Court by Levine Eisberner LLC and Siri & Glimstad on behalf of a project manager who claims that he was wrongfully terminated after applying for a religious exemption to the defendant's COVID-19 vaccine mandate. The case, assigned to U.S. Magistrate Judge Anita Marie Boor, is 3:24-cv-00630, Secker, Nathan v. Epic Systems Corporation.
Who Got The Work
David X. Sullivan, Thomas J. Finn and Gregory A. Hall from McCarter & English have entered appearances for Sunrun Installation Services in a pending civil rights lawsuit. The complaint was filed Sept. 4 in Connecticut District Court by attorney Robert M. Berke on behalf of former employee George Edward Steins, who was arrested and charged with employing an unregistered home improvement salesperson. The complaint alleges that had Sunrun informed the Connecticut Department of Consumer Protection that the plaintiff's employment had ended in 2017 and that he no longer held Sunrun's home improvement contractor license, he would not have been hit with charges, which were dismissed in May 2024. The case, assigned to U.S. District Judge Jeffrey A. Meyer, is 3:24-cv-01423, Steins v. Sunrun, Inc. et al.
Who Got The Work
Greenberg Traurig shareholder Joshua L. Raskin has entered an appearance for boohoo.com UK Ltd. in a pending patent infringement lawsuit. The suit, filed Sept. 3 in Texas Eastern District Court by Rozier Hardt McDonough on behalf of Alto Dynamics, asserts five patents related to an online shopping platform. The case, assigned to U.S. District Judge Rodney Gilstrap, is 2:24-cv-00719, Alto Dynamics, LLC v. boohoo.com UK Limited.
Featured Firms
Law Offices of Gary Martin Hays & Associates, P.C.
(470) 294-1674
Law Offices of Mark E. Salomone
(857) 444-6468
Smith & Hassler
(713) 739-1250