Jordan Jones and Goulding, Inc. “JJ&G”, a professional engineering firm, appeals from the trial court’s denial of its motion for summary judgment on the breach of contract claim asserted against it by Newell Recycling of Atlanta, Inc. “Newell”. JJ&G asserts that the trial court erred in finding that Newell’s claims were subject to the six-year statute of limitation applicable to actions on written contracts, as opposed to the four-year statute of limitation applicable to claims of professional malpractice sounding in contract. Alternatively, JJ&G argues that even if viewed as strictly a breach of contract action, Newell’s claim is subject to the four-year limitation period applicable to contracts that are partly in writing and partly in parol. We find that the record shows unequivocally that Newell is asserting a professional malpractice claim, based upon JJ&G’s alleged breach of its contractual duties to provide competent, professional design and engineering services. Thus, because Newell failed to file suit within the applicable, four-year limitation period, we reverse the trial court’s order. Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. On appeal from the grant or denial of a motion for summary judgment, we review the evidence de novo, and all reasonable conclusions and inferences drawn from the evidence are construed in the light most favorable to the nonmovant. Iwan Renovations, Inc. v. N. Atlanta Nat’l Bank .1 So viewed, the record shows that Newell is a corporation in the business of purchasing and processing scrap metal, which it then re-sells. In 1997, Newell contacted JJ&G about providing design and engineering services for a new automobile shredding facility it wanted to build in Gwinnett County. After several meetings with representatives from Newell, JJ&G prepared a proposal for the project, titled “Draft Scope of Work: Newell Recycling of Atlanta__,__ New Site —Duluth, Georgia,” and forwarded the same to Newell on August 15, 1997.2 Emphasis in original. The Draft Scope of Work outlined six different project phases that JJ&G proposed to work on and attached thereto was a detailed, five-page task list related to the first project phase, environmental site assessment. The cover letter that JJ&G sent to Newell with these documents explained: We are enclosing a draft Scope of Work which __we__ feel addresses our environmental assessment and permitting needs as well as facilities planning/design and bidding/construction phase needs for the New Recycling Facility in Duluth. We welcome your input . . . to ensure that we have covered all the bases. While you are reviewing this Scope of Work for completeness, we will be developing a budget estimate. On August 22, 1997, JJ&G sent Newell a second letter, providing them with a cost estimate for the first three project phases outlined in the Draft Scope of Work. The letter further stated: “The cost of the remaining 3 phases can not be accurately estimated until some definition of your proposed facilities can be developed and a site visit of the existing buildings and features can be arranged. We would propose to perform this work on an hourly bases and would only bill you for completed task.”
Representatives of Newell and JJ&G thereafter met several times to discuss and plan the details of the new facility and the engineering services that JJ&G would provide in connection with the project. By the spring of 1998, the parties had verbally agreed that there would be concrete pavement around the shredding machine to act as a work platform and to control drainage. JJ&G, therefore, developed a design for these pavements, which specified sub-grade preparation, concrete mix, and concrete thickness, and added this design to the site plans and specifications. Site construction began in the fall of 1998, with a firm other than JJ&G acting as the construction manager. During the course of construction, JJ&G made several revisions to the plans and specifications, including changes to the concrete pavement design. JJ&G made the last change to the concrete pavement design in June 1999, and completed all engineering work for such pavements by the end of July 1999. All engineering and construction work on the project was completed by the end of September 1999.