Publication Date: 2022-06-28
Practice Area: Contracts
Industry: Financial Services and Banking | Construction | Real Estate
Court: Delaware Superior Court
Judge: Judge Carpenter
Attorneys: For plaintiff: Blake A. Bennett, C. Scott Reese, Dean R. Roland, Cooch and Taylor, P.A., Wilmington, DE for plaintiff.
for defendant: David L. Baumberger, Law Offices of Chrissinger & Baumberger, Wilmington, DE; Kevin J. Connors, Marshall Dennehey Warner Coleman & Goggin, Wilmington, DE; Louis J. Rizzo, Jr., Reger Rizzo & Darnall LLP, Wilmington, DE; Josiah R. Wolcott, Connolly Gallagher, Newark, DE; Thaddeus J. Weaver, Dilworth Paxson LLP, Wilmington, DE for defendants.
Case Number: D69862
Defective construction claims by condominium association were timely filed where receiver who previously controlled condo was appointed solely to complete construction and limit the losses of the mortgagee, such that the limitations period did not start running until the association of ow ners took control.