'BHUSD v. FTA': How the Court Departed From NEPA's Presumptive Remedy to Justify a Popular Infrastructure Project
When a court finds that an agency has violated NEPA by overlooking or omitting an important impact from its review and remands the decision to the agency for further study, the court almost always vacates the record of decision associated with the project, stopping the project until the remand analysis is completed. In two recent decisions, however, courts departed from this presumptive remedy.
April 13, 2018 at 02:30 PM
9 minute read
The National Environmental Policy Act (NEPA) mandates that an agency reviewing an infrastructure project take a “hard look” at the project's environmental consequences before the agency decides to proceed. Because the timing of environmental analysis is critical for it to serve its intended purpose under environmental law, when a court finds that an agency has violated NEPA by overlooking or omitting an important impact from its review and remands the decision to the agency for further study, the court almost always vacates the record of decision (ROD) associated with the project, stopping the project until the remand analysis is completed.
In two recent decisions, however, courts departed from this presumptive remedy, permitting two of the biggest infrastructure projects in the United States—the Dakota Access Pipeline and the Westside Purple Line Subway Extension in Los Angeles—to proceed, notwithstanding findings that further environmental analysis was required as to each project. In both instances, the courts relied on the limited exception to the presumptive remedy articulated in Allied-Signal v. U.S. Nuclear Regulatory Commission, 988 F.2d 146 (D.C. Cir. 1996). In Allied-Signal, the court determined that remand without vacating the ROD is appropriate where there is a serious possibility that an agency will be able to substantiate its decision on remand and stopping the project will lead to impermissibly disruptive consequences in the interim.
Standing Rock Sioux Tribe v. U.S. Army Corps of Engineers, — F. Supp. 3d –, 2017 WL 4564714 (Oct. 11, 2017), concerning the Dakota Access Pipeline project, illustrates a proper application of Allied-Signal. There the U.S. District Court for the District of Columbia permitted the completed pipeline to operate pending a remand analysis because the U.S. Army Corps of Engineers (USACE) had substantially complied with NEPA. By contrast, in Beverly Hills Unified School District v. Federal Transit Administration, 2016 WL 4445770 (C.D. Cal. Aug. 12, 2016), a district court in the Central District of California made no such finding. But it nevertheless applied the holding in Allied-Signal, permitting the Federal Transit Administration (FTA) and the Los Angeles Country Metropolitan Transportation Authority (Metro) to enter into billions of dollars of contracts locking the alignment the agencies were ordered to reconsider on remand into place and undermining the purpose of NEPA.
The 'Standing Rock' Decision
In Standing Rock, the court found that the environmental assessment for the Dakota Access Pipeline—a 1,172 mile underground oil pipeline—“substantially complied” with NEPA and upheld the majority of determinations by the USACE, including the agency's central conclusion that the risk of an oil spill was sufficiently low that an environmental impact statement did not need to be prepared. Beyond this core holding that the environmental analysis was sound in principle, the court found three discrete deficiencies in the agency's analysis.
In determining the appropriate remedy for the identified errors, the court reiterated the longstanding rule that “vacating a rule or action promulgated in violation of NEPA is the standard remedy.” The District Court then analyzed whether the factual circumstances in Standing Rock “merit[] departure from the presumptive remedy of vacatur.” Addressing the Allied Signal factors, the court concluded that the agency's three errors did not present “fundamental flaws in [the agency's] reasoning” and the record demonstrated a “significant likelihood” that USACE would substantiate its decision on remand. The court reached this conclusion because USACE had “already gathered” and analyzed relevant data or information, and needed to “simply connect the dots,” “better articulat[e] their reasoning,” or explain “already-conducted” analysis to substantiate its prior conclusions.
While the court acknowledged that stopping operation of the pipeline pending the remand analysis would have “some disruptive effect,” the court cautioned against placing too much emphasis on disruption in reaching its conclusion because such emphasis might incentivize agencies and third parties to devote as many resources to a project “as early as possible … and then claim disruption in light of such investments,” promoting an “act first and ask later” attitude which is directly contrary to NEPA's purpose. Thus, the court held that effect of disruption was “only barely relevant” and remanded without vacatur based on its findings that the agency's “errors are likely to be cured.”
The 'Beverly Hills' Decision
The dangers of emphasizing the disruptive consequences of vacatur the Standing Rock court warned about are illustrated in the Beverly Hills case. There, the court held that the FTA violated NEPA and §4(f) of the Department of Transportation Act when it failed to analyze environmental impacts of the Westside Purple Line Extension—a popular project in traffic-congested Los Angeles that will extend the city's subway to a new western terminus located near the West Los Angeles Veteran Affairs Hospital. Among other deficiencies, the court found that the FTA violated §4(f) when it determined that tunneling underneath Beverly Hills High School—the only public high school in the city of Beverly Hills—was not a “use” of protected historic and recreational resources on the High School campus, and “consequently fail[ed] to undertake the follow-on §4(f) analysis” of feasible and prudent alternative alignments and all possible planning to minimize harm to those resources. (This article focuses on the court's conclusion that the FTA failed to engage in the requisite §4(f) alternatives analysis. In addition to this error, the court identified three other principal violations of NEPA which it ordered the FTA to address in a supplemental analysis on remand.)
Notwithstanding the FTA's conceded failure to conduct any alternatives analysis of feasible and prudent alternatives to the use of the High School's historic and recreational resources, the court declined to vacate the record of decision for the project. Rather, rejecting the longstanding principle that vacatur is the presumptive remedy for agency action that violates NEPA, the court held that an analysis of the Allied Signal factors dictate that remand, without vacatur, was the appropriate remedy.
In reaching this conclusion, the court gave short-shrift to consideration of the seriousness of the FTA's errors, holding—in a single conclusory paragraph—that “there is no indication that the FTA would be unable to offer better and/or more complete reasoning for its challenged decisions.” The court failed to identify any evidence in the record, such as “already conducted” analyses, that would allow the agency to substantiate or better articulate its reasoning. This is because the FTA's erroneous determination that there would be no “use” of the school campus resulted in the FTA never having conducted the requisite §4(f) analysis in the first instance.
While NEPA mandates that §4(f)'s feasible and prudent alternatives analysis be conducted prior to the point of commitment to a particular alignment, the court held that the claimed disruptive consequences of vacating the ROD weighed against stopping the project during remand. Those disruptive consequences included the delay in executing, the Full Funding Grant Agreement (FFGA), a binding commitment to award $1.187 billion in federal funds. Without the FFGA, the project sponsor, Metro, would be unable to award binding contracts to design and build the subway alignment.
The determinative effect given to the FTA and Metro's claimed disruptive consequences of vacating the ROD in the Beverly Hills case resulted in the court granting the agencies license to execute binding contracts committing multi-billion dollars in resources to the alignment under consideration before the remand analysis was complete. In making the decision, the court acknowledged testimony from Metro's CEO that executing the FFGA would prejudice the evaluation of alignments on remand because any changes would jeopardize federal funding, but nevertheless found that a desire to avoid a delay in realizing the project's benefits justified applying the Allied-Signal exemption.
When Courts Should Depart From the Presumptive Remedy
Applied properly, Allied-Signal permits agencies to avoid disrupting infrastructure projects in limited circumstances where an agency has substantially complied with NEPA and record evidence demonstrates a significant likelihood that on remand the agency will be able to substantiate its prior conclusion based on previously gathered and analyzed data.
But courts should be cautious not to expand the Allied-Signal exception to justify popular infrastructure projects where there is no evidence in the record that the agency previously conducted the required environmental review. Failing to vacate the record of decision in the absence of such evidence will enable an infrastructure project that has not been adequately analyzed to proceed, undermining NEPA's central purpose and resulting in environmental harm. As courts have repeatedly recognized, NEPA does not set out substantive environmental standards, but instead establishes “action-forcing” procedures to ensure that agencies meet their obligations. In this way, NEPA simply guarantees a particular procedure, rather than a substantive result. Consistent with its central purpose, NEPA requires that environmental analysis be completed before the agency commits to a project design, so that the analysis can serve practically in the decision-making process and will not be used to rationalize or justify decisions already made.
In declining to vacate, the Beverly Hills court permitted the FTA and Metro to execute multi-billion dollar contracts for the construction of the subway tunnels beneath the high school and spend hundreds of millions of dollars in federal funds on the alignment as designed before the agencies conducted any analysis of alternative alignments. Departing from the presumptive remedy of vacatur under these circumstances undermines NEPA's purpose. Numerous courts have recognized that such a commitment of resources will inevitably restrict the agency's options. Either the project planners will have to undergo a major expense in making alterations or the environmental harm will have to be tolerated. It is all too probable that the latter result will come to pass. Lathan v. Volpe, 455 F.2d 1111, 1121 (9th Cir. 1971).
Jennifer S. Recine is a litigation partner and member of the management committee, Lauren Tabaksblat is a litigation partner, and Tiffany L. Ho is a litigation associate at Kasowitz Benson Torres in New York. Ms. Recine and Ms. Tabaksblat represented the Beverly Hills Unified School District in a NEPA action against the FTA. That case was dismissed on Jan. 23, 2018; on February 8, a new matter was filed on behalf of the school against the FTA, in addition to the Los Angeles Metro.
This content has been archived. It is available through our partners, LexisNexis® and Bloomberg Law.
To view this content, please continue to their sites.
Not a Lexis Subscriber?
Subscribe Now
Not a Bloomberg Law Subscriber?
Subscribe Now
NOT FOR REPRINT
© 2025 ALM Global, LLC, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more information visit Asset & Logo Licensing.
You Might Like
View AllThe Unraveling of Sean Combs: How Legislation from the #MeToo Movement Brought Diddy Down
When It Comes to Local Law 97 Compliance, You’ve Gotta Have (Good) Faith
8 minute readTrending Stories
- 1DC Bar’s Proposed Anti-Discrimination, Harassment Conduct Rule Sees More Pushback
- 2California's Chief Justice Starts Third Year With Questions About Fires, Trump and AI
- 3Justin Baldoni Sues Blake Lively and Ryan Reynolds for $400M in New Step in 'It Ends With Us' Fight
- 4Top Leadership Changes Coming for NJ Attorney General's Office
- 5SCOTUSBlog Co-Founder Tom Goldstein Misused Law Firm Funds, According to Federal Indictment
Who Got The Work
J. Brugh Lower of Gibbons has entered an appearance for industrial equipment supplier Devco Corporation in a pending trademark infringement lawsuit. The suit, accusing the defendant of selling knock-off Graco products, was filed Dec. 18 in New Jersey District Court by Rivkin Radler on behalf of Graco Inc. and Graco Minnesota. The case, assigned to U.S. District Judge Zahid N. Quraishi, is 3:24-cv-11294, Graco Inc. et al v. Devco Corporation.
Who Got The Work
Rebecca Maller-Stein and Kent A. Yalowitz of Arnold & Porter Kaye Scholer have entered their appearances for Hanaco Venture Capital and its executives, Lior Prosor and David Frankel, in a pending securities lawsuit. The action, filed on Dec. 24 in New York Southern District Court by Zell, Aron & Co. on behalf of Goldeneye Advisors, accuses the defendants of negligently and fraudulently managing the plaintiff's $1 million investment. The case, assigned to U.S. District Judge Vernon S. Broderick, is 1:24-cv-09918, Goldeneye Advisors, LLC v. Hanaco Venture Capital, Ltd. et al.
Who Got The Work
Attorneys from A&O Shearman has stepped in as defense counsel for Toronto-Dominion Bank and other defendants in a pending securities class action. The suit, filed Dec. 11 in New York Southern District Court by Bleichmar Fonti & Auld, accuses the defendants of concealing the bank's 'pervasive' deficiencies in regards to its compliance with the Bank Secrecy Act and the quality of its anti-money laundering controls. The case, assigned to U.S. District Judge Arun Subramanian, is 1:24-cv-09445, Gonzalez v. The Toronto-Dominion Bank et al.
Who Got The Work
Crown Castle International, a Pennsylvania company providing shared communications infrastructure, has turned to Luke D. Wolf of Gordon Rees Scully Mansukhani to fend off a pending breach-of-contract lawsuit. The court action, filed Nov. 25 in Michigan Eastern District Court by Hooper Hathaway PC on behalf of The Town Residences LLC, accuses Crown Castle of failing to transfer approximately $30,000 in utility payments from T-Mobile in breach of a roof-top lease and assignment agreement. The case, assigned to U.S. District Judge Susan K. Declercq, is 2:24-cv-13131, The Town Residences LLC v. T-Mobile US, Inc. et al.
Who Got The Work
Wilfred P. Coronato and Daniel M. Schwartz of McCarter & English have stepped in as defense counsel to Electrolux Home Products Inc. in a pending product liability lawsuit. The court action, filed Nov. 26 in New York Eastern District Court by Poulos Lopiccolo PC and Nagel Rice LLP on behalf of David Stern, alleges that the defendant's refrigerators’ drawers and shelving repeatedly break and fall apart within months after purchase. The case, assigned to U.S. District Judge Joan M. Azrack, is 2:24-cv-08204, Stern v. Electrolux Home Products, Inc.
Featured Firms
Law Offices of Gary Martin Hays & Associates, P.C.
(470) 294-1674
Law Offices of Mark E. Salomone
(857) 444-6468
Smith & Hassler
(713) 739-1250