An Owner's Response to Potential Subcontractor Liens
In their Construction Law column, Kenneth Block and Josh Levy consider the scenario when your client is the owner of a construction project nearing completion when she is approached by her general contractor that he owes more money to his subcontractor than she will owe to him, and also a mechanic's lien has been filed by one of his subcontractors. What are your client's options if she doesn't want to increase the contract sum and continue working with the general contractor?
November 13, 2018 at 02:30 PM
5 minute read
Consider this scenario: Your client is the owner of a construction project nearing completion when she is approached by her general contractor and told that he owes more money to his subcontractor than she owes (or will owe) to him. To add to the distress, a mechanic's lien has been filed by one of his subcontractors and your client is concerned that additional liens may be filed. What are your client's options if she does not wish to increase the contract sum and continue working with the general contractor?
Addressing your client's concern regarding existing and future liens, it must first be noted that while the unpaid subcontractors can file notices of lien for the full amount owed by the general contractor, the owner's liability for such liens is limited by the amount unpaid to the general contractor at the time of the filing of the liens. This unpaid amount is known as the “lien fund.” Thus, in the absence of a lien fund, a lien by a subcontractor is invalid against an owner. In our scenario, however, your client has exposure to the previously filed lien because, at the time of the filing, monies were due to the general contractor.
A Successful Approach
An approach we have successfully followed in these circumstances involved the consensual termination of the general contractor and the payment in full of all monies then due to the general contractor, subject to an escrow payment to its counsel to cover the cost of satisfying the existing lien. This approach allowed for a clean break with the general contractor and provided substantial funds—trust funds under the Lien Law—for payment to the subcontractors and to cover permissible reimbursement for fee and general conditions to the general contractor. The general contractor, of course, remained liable to its subcontractors for any shortfalls due to the subcontractors.
In following this approach, we relied on the Lien Law and ancient common law principles that, in the absence of fraud, an owner cannot be compelled to pay any greater sum for the completion of a project than he has agreed to pay his general contractor, and that such payments cannot be attacked by subsequent lienors. Some two months after the owner settled in full with the general contractor, and extinguished the lien fund, a notice of mechanic's lien was filed by a subcontractor, followed by a lien foreclosure action which included claims for trust fund diversions against the general contractor. After extensive discovery, we moved to dismiss the action against the owner.
In opposition to our motion to dismiss, the subcontractor argued, among other things, that the owner had no right to, in effect, terminate the contract “for convenience,” as opposed to “for cause,” and that the final payment was actually an impermissible payment “in advance “ under Section 7 of the Lien Law. (“Any payment by the owner, contractor or subcontractor upon a contract for the improvement of real property, made prior to the time when, by the terms of the contract, such payment becomes due, for the purpose of avoiding the provisions of this article, shall be of no effect as against the lien of a subcontractor, laborer, or materialman under such contract, created before such payment actually becomes due.”)
Thus, the essential question for the court was whether the owner had the right to terminate the general contract for convenience and make final payment upon such termination. In 3-G Services Limited v. Sap V/Atlas 845 WEA Associates NF LLC, (2017 N.Y. Slip Op. 31593(U), [Sup Ct, NY County 2017]), the Supreme Court ruled for the owner.
In 3-G Services, Justice Joan Madden held that under the specific facts presented, the lienor would not be able to foreclose on its lien, even though the contractor was terminated for convenience prior to the final completion of the project. The contractual termination for convenience provision allowed the owner to terminate at any time, and the general contractor would only be entitled to monies due and owing for work performed as of that date. In affirming, the Appellate Division found that the final payment to the general contractor was not an advance payment under Section 7. 3-G Services Limited v. SAP V/Atlas 845 WEA Associates NF LLC., aff'd, 162 A.D.3d 487 (1st Dept. 2018). The court also addressed the lienor's arguments of bad faith and concluded that neither the owner's knowledge that monies were due to the lienor nor its election to terminate for convenience demonstrated bad faith.
Back to the Scenario
Returning to our scenario, you first must reach agreement in concept with the general contractor regarding termination and final payment. Although the general contract may allow for termination for convenience, the general contractor may prefer a mutual termination. A final requisition should then be provided by the contractor and a lien search performed by the owner. Once the final amount has been agreed upon it can be paid in exchange for a final waiver and release of lien. To the extent that liens exist, a separate escrow should be established to facilitate payment.
As to the claims of the subcontractors, the final payment to the general contractor will be considered trust funds and the general contractor should provide an indemnity to the owner against such claims if one does not already exist in the general contract. While there are no guarantees, this course should protect the owner against liability for subsequently filed notices of lien.
|This content has been archived. It is available through our partners, LexisNexis® and Bloomberg Law.
To view this content, please continue to their sites.
Not a Lexis Subscriber?
Subscribe Now
Not a Bloomberg Law Subscriber?
Subscribe Now
NOT FOR REPRINT
© 2024 ALM Global, LLC, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more information visit Asset & Logo Licensing.
You Might Like
View AllThe Unraveling of Sean Combs: How Legislation from the #MeToo Movement Brought Diddy Down
When It Comes to Local Law 97 Compliance, You’ve Gotta Have (Good) Faith
8 minute readTrending Stories
Who Got The Work
Michael G. Bongiorno, Andrew Scott Dulberg and Elizabeth E. Driscoll from Wilmer Cutler Pickering Hale and Dorr have stepped in to represent Symbotic Inc., an A.I.-enabled technology platform that focuses on increasing supply chain efficiency, and other defendants in a pending shareholder derivative lawsuit. The case, filed Oct. 2 in Massachusetts District Court by the Brown Law Firm on behalf of Stephen Austen, accuses certain officers and directors of misleading investors in regard to Symbotic's potential for margin growth by failing to disclose that the company was not equipped to timely deploy its systems or manage expenses through project delays. The case, assigned to U.S. District Judge Nathaniel M. Gorton, is 1:24-cv-12522, Austen v. Cohen et al.
Who Got The Work
Edmund Polubinski and Marie Killmond of Davis Polk & Wardwell have entered appearances for data platform software development company MongoDB and other defendants in a pending shareholder derivative lawsuit. The action, filed Oct. 7 in New York Southern District Court by the Brown Law Firm, accuses the company's directors and/or officers of falsely expressing confidence in the company’s restructuring of its sales incentive plan and downplaying the severity of decreases in its upfront commitments. The case is 1:24-cv-07594, Roy v. Ittycheria et al.
Who Got The Work
Amy O. Bruchs and Kurt F. Ellison of Michael Best & Friedrich have entered appearances for Epic Systems Corp. in a pending employment discrimination lawsuit. The suit was filed Sept. 7 in Wisconsin Western District Court by Levine Eisberner LLC and Siri & Glimstad on behalf of a project manager who claims that he was wrongfully terminated after applying for a religious exemption to the defendant's COVID-19 vaccine mandate. The case, assigned to U.S. Magistrate Judge Anita Marie Boor, is 3:24-cv-00630, Secker, Nathan v. Epic Systems Corporation.
Who Got The Work
David X. Sullivan, Thomas J. Finn and Gregory A. Hall from McCarter & English have entered appearances for Sunrun Installation Services in a pending civil rights lawsuit. The complaint was filed Sept. 4 in Connecticut District Court by attorney Robert M. Berke on behalf of former employee George Edward Steins, who was arrested and charged with employing an unregistered home improvement salesperson. The complaint alleges that had Sunrun informed the Connecticut Department of Consumer Protection that the plaintiff's employment had ended in 2017 and that he no longer held Sunrun's home improvement contractor license, he would not have been hit with charges, which were dismissed in May 2024. The case, assigned to U.S. District Judge Jeffrey A. Meyer, is 3:24-cv-01423, Steins v. Sunrun, Inc. et al.
Who Got The Work
Greenberg Traurig shareholder Joshua L. Raskin has entered an appearance for boohoo.com UK Ltd. in a pending patent infringement lawsuit. The suit, filed Sept. 3 in Texas Eastern District Court by Rozier Hardt McDonough on behalf of Alto Dynamics, asserts five patents related to an online shopping platform. The case, assigned to U.S. District Judge Rodney Gilstrap, is 2:24-cv-00719, Alto Dynamics, LLC v. boohoo.com UK Limited.
Featured Firms
Law Offices of Gary Martin Hays & Associates, P.C.
(470) 294-1674
Law Offices of Mark E. Salomone
(857) 444-6468
Smith & Hassler
(713) 739-1250