COVID-19, Force Majeure and the Entertainment Industry
In their Entertainment Law column, Michael I. Rudell and Neil J. Rosini explore one of the big questions for contracting parties in the midst of this pandemic: whether force majeure will excuse or postpone a party's obligations without liability.
July 31, 2020 at 12:30 PM
7 minute read
The COVID-19 outbreak has wreaked havoc on the entertainment industry. Productions have been halted and distribution channels disrupted, causing a massive shift for both industry insiders and consumers alike. Live events now are being experienced via various streaming platforms as the doors to movie theaters, Broadway houses and concert venues remain shuttered. Unsurprisingly, numerous entertainment contracts have been thrown off course, due to governmental orders prohibiting production activities, the expiration of unmet payment and delivery deadlines, cast and crew fears of becoming ill, and the costs inherent in resuming activities in this new environment.
In the midst of this pandemic, one big question for contracting parties is whether force majeure will excuse or postpone a party's obligations without liability. A force majeure, or a so-called "Act of God" clause, generally allows a party to suspend and also terminate a contract without liability if an unforeseen event beyond the party's control makes performance of the party's obligations impossible or impractical. Before the entertainment industry was turned upside down by COVID-19, force majeure clauses were not a primary focus, and were likely buried in the boilerplate language, often ignored and rarely negotiated. Now, as actors, writers, producers, directors, and production companies alike have found their income streams disrupted and their services deferred by letters invoking force majeure clauses, the entertainment industry is paying much closer attention.
Here are five things to bear in mind about a force majeure provision and its implications:
- Even with a force majeure clause, the grounds to excuse performance may be limited.
Force majeure derives from the common law doctrine of impossibility, which has very narrow application. Under the doctrine of impossibility, to excuse a party's non-performance, the subject matter of the agreement or the means of performance must become objectively impossible. A typical example is destruction of property that makes performance of a contract impossible. But whether or not COVID-19 in given instances will meet the stringent criteria of impossibility is far from predictable. A well-drafted force majeure clause could remove that uncertainty, but just like the doctrine of impossibility, courts interpret force majeure clauses narrowly, and it is important to draft them with specificity.
- What does a force majeure clause say?
A force majeure clause allows contracting parties to allocate risks relating to unforeseen events beyond their control. Generally, force majeure clauses: (i) identify events that, should they occur, would excuse a party's non-performance (so-called "force majeure events"); and (ii) specify the scope of recourse available to an affected party (e.g., to suspend production or the obligation to furnish services). Force majeure events typically include a list of specific events like "war, fire, flood, and governmental order or regulation." In entertainment contracts, they may also specifically include reference to events that would delay or impede the development, production or exhibition of a given project, such as union or guild strikes and the death, incapacity, unavailability or default of the director or any principal cast member of the project. Many clauses also include a catch-all specifying that force majeure events include any event "outside the control" of the parties, but the particular wording of such clauses determines whether and how they apply.
The list of force majeure events should be as exhaustive and specific as possible because of courts' narrow interpretations. However, even if a clause does not expressly identify a particular force majeure event (e.g., by referring explicitly to a "pandemic"), it may still include an event that is close enough to excuse non-performance under the force majeure clause (e.g., by referring to an "epidemic"). In the absence of a detailed clause, or one that does not precisely specify the event, a court might conclude that a party affected by a particular event assumed that risk and cannot suspend or terminate its obligations.
- What is the scope of recourse permitted by a force majeure clause?
The scope of recourse permitted by a force majeure clause depends to a large extent on how it is drafted. It might allow the breaching party to suspend or terminate all obligations under a given contract, or it may allow only partial recourse. For example, for a contract entered into before the initial COVID-19 outbreak under which a producer is obligated to deliver a documentary feature by a certain deadline, the producer may be able to invoke a force majeure provision that includes an epidemic as a force majeure event if, due to COVID-19, the producer's crew can no longer travel to film the documentary's subjects in the intended locations. Depending on the text of the clause, the producer may have the right to deliver a different version of the project than was originally intended, postpone delivery for a certain period of time, or terminate the agreement altogether.
- If obligations are suspended, when will they be reinstated?
If a force majeure clause allows for obligations under the contract to be suspended, typically the duration for suspension will be for as long as the applicable force majeure event continues, and perhaps even for a reasonable time following the event to allow for the resumption of normal activities.
Sometimes, however, parties negotiate for the force majeure suspension period to be limited to a maximum time period (e.g., six months). After that period expires, the contract might entitle either party to terminate the agreement, or it might reinstate certain obligations even if the applicable force majeure event continues.
Without clear details in the clause, it may be difficult to know when the duration of a force majeure event has ended and contractual obligations are restored, such as payment and delivery deadlines. This is especially the case for the current pandemic. Unlike a discrete event such as work stoppage caused by a union strike that would have a clear resolution, the end date of the current crisis may not be indisputable.
- For entertainment contracts going forward, issues related to COVID-19 should be addressed directly and separately from other force majeure contingencies.
As parties negotiate new agreements for rendering services or granting rights, both sides need to consider how their expectations might be affected by COVID-19 and address them explicitly within the contract. This is the best way to avoid uncertainty, particularly because courts generally require force majeure events to be unforeseeable, and the pandemic is no longer an unforeseen occurrence.
One approach might be to agree—separate from other force majeure contingencies—that certain obligations can be suspended due to COVID-19 effects but with an outside date for their performance, failing which either party would have the right to terminate the agreement. A licensor may agree to an extension of a license period at least for a period of time, perhaps if some payment is still being made, but will want to know that a suspension will not tie up a property indefinitely.
Other obligations might be required to continue. For example, a production agreement might require strict adherence to a timeline for activities that can be done remotely, like script writing and preproduction planning notwithstanding COVID-19 issues, while allowing for postponement of principal photography. A more complicated scenario would allocate the risk of a shutdown once production has commenced particularly if COVID-19 effects are not covered by insurance.
Parties would be wise to consider such possibilities in the current environment and specify directly and separately the effect that COVID-19 will have on their obligations, either within a force majeure clause or in a distinct contractual provision.
Neil J. Rosini and Michael I. Rudell are partners in Franklin, Weinrib, Rudell & Vassallo. Both practice entertainment law and have written and lectured extensively on the subject. They gratefully acknowledge the assistance of Richard A. Beyman, a partner of the firm, and Eve Nguyen, an associate of the firm, in the preparation of this article.
This content has been archived. It is available through our partners, LexisNexis® and Bloomberg Law.
To view this content, please continue to their sites.
Not a Lexis Subscriber?
Subscribe Now
Not a Bloomberg Law Subscriber?
Subscribe Now
NOT FOR REPRINT
© 2024 ALM Global, LLC, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more information visit Asset & Logo Licensing.
You Might Like
View AllPost-Pandemic Increase in Live Events Prompts Need for Premise Liability Action
7 minute readAs Uncertainty Hovers Over PGA Merger, LIV Golf Hires Entertainment Industry Veteran as Legal Chief
'Rampant Piracy': US Record Labels File Copyright Suit Against French Distributor Believe
5 minute readTrending Stories
- 1Saying Your Goodbyes—Ethical Obligations When Transitioning to a New Firm
- 2Woman's Suit Alleging Negligence to Sex Trafficking by Hotel Tossed by Federal Judge
- 3Dog Gone It, Target: Provider of Retailer's Mascot Dog Sues Over Contract Cancellation
- 4Lululemon Faces Legal Fire Over Its DEI Program After Bias Complaints Surface
- 5Plaintiff Gets $500K Policy Limit Without Surgery
Who Got The Work
Michael G. Bongiorno, Andrew Scott Dulberg and Elizabeth E. Driscoll from Wilmer Cutler Pickering Hale and Dorr have stepped in to represent Symbotic Inc., an A.I.-enabled technology platform that focuses on increasing supply chain efficiency, and other defendants in a pending shareholder derivative lawsuit. The case, filed Oct. 2 in Massachusetts District Court by the Brown Law Firm on behalf of Stephen Austen, accuses certain officers and directors of misleading investors in regard to Symbotic's potential for margin growth by failing to disclose that the company was not equipped to timely deploy its systems or manage expenses through project delays. The case, assigned to U.S. District Judge Nathaniel M. Gorton, is 1:24-cv-12522, Austen v. Cohen et al.
Who Got The Work
Edmund Polubinski and Marie Killmond of Davis Polk & Wardwell have entered appearances for data platform software development company MongoDB and other defendants in a pending shareholder derivative lawsuit. The action, filed Oct. 7 in New York Southern District Court by the Brown Law Firm, accuses the company's directors and/or officers of falsely expressing confidence in the company’s restructuring of its sales incentive plan and downplaying the severity of decreases in its upfront commitments. The case is 1:24-cv-07594, Roy v. Ittycheria et al.
Who Got The Work
Amy O. Bruchs and Kurt F. Ellison of Michael Best & Friedrich have entered appearances for Epic Systems Corp. in a pending employment discrimination lawsuit. The suit was filed Sept. 7 in Wisconsin Western District Court by Levine Eisberner LLC and Siri & Glimstad on behalf of a project manager who claims that he was wrongfully terminated after applying for a religious exemption to the defendant's COVID-19 vaccine mandate. The case, assigned to U.S. Magistrate Judge Anita Marie Boor, is 3:24-cv-00630, Secker, Nathan v. Epic Systems Corporation.
Who Got The Work
David X. Sullivan, Thomas J. Finn and Gregory A. Hall from McCarter & English have entered appearances for Sunrun Installation Services in a pending civil rights lawsuit. The complaint was filed Sept. 4 in Connecticut District Court by attorney Robert M. Berke on behalf of former employee George Edward Steins, who was arrested and charged with employing an unregistered home improvement salesperson. The complaint alleges that had Sunrun informed the Connecticut Department of Consumer Protection that the plaintiff's employment had ended in 2017 and that he no longer held Sunrun's home improvement contractor license, he would not have been hit with charges, which were dismissed in May 2024. The case, assigned to U.S. District Judge Jeffrey A. Meyer, is 3:24-cv-01423, Steins v. Sunrun, Inc. et al.
Who Got The Work
Greenberg Traurig shareholder Joshua L. Raskin has entered an appearance for boohoo.com UK Ltd. in a pending patent infringement lawsuit. The suit, filed Sept. 3 in Texas Eastern District Court by Rozier Hardt McDonough on behalf of Alto Dynamics, asserts five patents related to an online shopping platform. The case, assigned to U.S. District Judge Rodney Gilstrap, is 2:24-cv-00719, Alto Dynamics, LLC v. boohoo.com UK Limited.
Featured Firms
Law Offices of Gary Martin Hays & Associates, P.C.
(470) 294-1674
Law Offices of Mark E. Salomone
(857) 444-6468
Smith & Hassler
(713) 739-1250