Enforceability of Oral Change Orders Despite 'No Oral Modification' Clauses
Most construction contracts contain one or more NOM clauses, including a requirement that valid change orders be in writing. Generally, these clauses provide that a contract cannot be modified absent a writing executed by the parties.
July 02, 2020 at 12:37 PM
9 minute read
The recent decision in STI Oilfield Services v. The Williams Companies, Inc. f/k/a Access Midstream Partners, No. 2018-1003 C.P. (Pa. Com. Pl., Susquehanna County, March 16, 2020 Opinion), highlights the challenges those in the construction industry face when contractors or subcontractors seek additional compensation based upon an alleged oral change order or modification, even when the underlying contract contains a clear "no oral modification" (NOM) clause.
Most construction contracts contain one or more NOM clauses, including a requirement that valid change orders be in writing. Generally, these clauses provide that a contract cannot be modified absent a writing executed by the parties. This is intended to avoid having the carefully drafted written agreement of the parties set aside based on alleged oral conversations that are often supported only by memory or by piecing together evidence of conduct of the parties. Oral modifications naturally breed disagreements, misunderstandings and protracted litigation—everything a well-written contract seeks to avoid. However, Pennsylvania courts have not strictly enforced NOM clauses, especially with respect to construction contracts and alleged oral change orders for extra work.
In Universal Builders v. Moon Motor Lodge, 244 A.2d 10, 15 (Pa. 1968) the Pennsylvania Supreme Court held that, outside of a contract subject to the statute of frauds, a written "contract can be modified orally although it provides that it can be modified only in writing." "Construction contracts typically provide that the builder will not be paid for extra work unless it is done pursuant to a written change order, yet courts frequently hold that owners must pay for extra work done at their oral direction." "The effectiveness of a nonwritten modification in spite of a contract condition that the modifications must be written depends upon whether enforcement of the condition is or is not barred by equitable considerations, not upon the technicality of whether the condition was or was not expressly and separately waived before the non-written modification."
Courts have significant discretion in determining whether to allow oral modification claims to survive dispositive motions and move to trial. When exercising that discretion, courts look to multiple equitable factors including estoppel, the "waiver of the [NOM] or the existence of some sort of fraud, mistake, accident or reliance." See Delaware River Port Authority v. Thornburgh, 585 A.2d 1123, 1128 (Pa. Commw. Ct. 1989) (citing Universal Builders, 244 A.2d at 16). The evidentiary standard generally required for proving oral modification of a written agreement is "clear and convincing evidence," but the protection this higher standard offers to contracting parties who do not believe an oral modification occurred often arrives too late, at trial after incurring significant litigation costs.
In Somerset Community Hospital v. Allan B. Mitchell & Associates, 685 A.2d 141, 146 (Pa. Super. Ct. 1996), the Superior Court was presented with the issue of whether an architect who performed design work for a hospital was entitled to seek additional fees for its alleged increased scope of work based upon oral agreements with the hospital, even where the underlying contract contained an NOM clause. The court determined that "an agreement that prohibits nonwritten modification may be modified by subsequent oral agreement if the parties' conduct clearly shows the intent to waive the requirement that the amendments be made in writing," (citing Accu-Weather v. Prospect Communications, 644 A.2d 1251 (Pa. Super. Ct. 1994)). Specifically, the court looked to the parties' conduct and determined that the parties' representatives' actions effectively waived the no-written modification clause of the contract.
In James v. N. Allegheny School District, 938 A.2d 474, 487 (Pa. Commw. Ct. 2007), the Pennsylvania Commonwealth Court held that a contractor could recover its costs for extra work even though it did not comply with the NOM clause and written notice provisions contained in the contract. In making its decision, the court considered similar factors to those in Somerset Community Hospital, Delaware River and Universal Builders.These included that the owner's representative orally directed the extra work; the owner had knowledge the work was performed and the associated costs; the contractor submitted written documentation of the extra work after it was performed; and the owner was not materially prejudiced by the late notice of the extra work claim. Thus, based on those factors, the court concluded, "Owner, having directed contractor to perform the additional work asserting it was required by contract, cannot now disavow liability for costs incurred by claiming Contractor did not have written authorization," (citing A.G. Cullen Construction v. State System of Higher Education, 898 A.2d 1145, 1171 (Pa. Commw. Ct. 2006) and Derry Township School District v. Suburban Roofing, 517 A.2d 225 (Pa. Commw. Ct. 1986)).
In STI Oilfield, the court addressed these legal issues in the context of written contracts between the project owner and contractor for four pipeline construction projects. After the projects were substantially completed, the contractor notified the owner of change order claims totaling almost double the aggregate original contract price. STI Oilfield, No. 2018-1003 C.P., p. 9 (March 16, 2020 Opinion).
None of the contractor's claims complied with contract provisions regarding notice, written change order procedures or the general NOM clause. In many instances, the alleged extra work at issue occurred months prior to the owner receiving notice of the claim. The most significant claim was based on alleged oral agreements made prior to entering the contract and during its performance that purportedly required the owner to compensate the contractor for additional costs due to adverse weather conditions. This alleged oral agreement directly contradicted the written contract terms, which expressly provided the contractor was not entitled to additional compensation due to weather. The other claims largely involved more standard allegations of extra work, such as removal of rock from the right-of-way, preparation for a hurricane, and additional labor and materials to comply with an updated winter work specification.
Judge Jason Legg of the Susquehanna County Common Pleas Court granted partial summary judgment on the most significant change order claim regarding adverse weather costs. Citing Nicolella v. Palmer, 248 A.2d 20, 23 (Pa. 1968) and persuasive authority of Smith v. Phillips Pipe Line, 128 F.Supp. 61 (N.D. Okla. 1955), Legg found the parol evidence rule barred evidence of alleged pre-contract oral agreements concerning extra compensation due to weather. The court further held the claims related to the alleged post-contract oral agreement regarding weather costs failed because the contract language precluding additional compensation due to weather prevented any finding that the cost overruns could constitute extra work. The court further reasoned that even if the alleged subsequent oral modifications occurred, they were unenforceable due to lack of consideration since adverse weather was included in the original scope of the contract. The court held that performance of a preexisting contractual duty cannot constitute consideration for a contract modification.
However, Legg refused to dismiss the contractor's other claims for alleged out-of-scope work. Legg followed an earlier decision in the case that relied on the reasoning of James and related precedent in allowing the claims to survive summary judgment and move to trial. The court that held noncompliance with the NOM clause and written change order provisions was not sufficient to dismiss the claims as a matter of law because questions of fact existed as to whether the contractor was directed to perform extra work and whether noncompliance with the contract caused prejudice to the owner. Thus, despite the existence of NOM provisions, the court found the contractor's testimony of an oral agreement and performance of the work was sufficient to avoid summary judgment.
When drafting construction contracts, parties should keep these cases in mind and seek to craft provisions that go beyond the standard NOM clause or written change order provision to avoid disputes and protracted litigation regarding oral modification. The potential options are limited only by the parties' creativity and circumstances of the transaction. The following are a few provisions to consider: requiring the contractor/subcontractor deliver advance written notice of the extra work to specific nonfield personnel as a condition precedent to authority to perform the work; making a signed written change order an express condition precedent to authority to perform extra work and receive payment; defining the personnel who have authority, and the extent of their authority, to modify the contract or order extra work; express language that the parties agree failure to comply with the change order provisions will cause material prejudice, and perhaps even listing the reasons why; defining the necessary evidentiary support that must be submitted with a change order, including tracking extra work costs; identifying a definite claim deadline upon which a party forfeits or waives a claim; and utilizing broad claim waiver forms the contractor/subcontractor must submit with each pay application, including progress payments and final payment, as a condition precedent to payment. These contractual tactics may not eliminate the risk posed by claims of oral modification, but they serve to encourage timely submission of legitimate claims, discourage the fabrication of oral change order claims, and promote the early resolution of claims if litigation ensues.
James D. Miller is a shareholder in the construction and litigation groups of Babst Calland Clements & Zomnir. He advises companies in the construction and energy industries, including contractors, subcontractors, suppliers and project owners, with issues related to contract drafting, project management, dispute resolution and general business consultation. Contact him at 412-394-6438 or [email protected]
Benjamin R. Wright is an associate in the construction and litigation groups of the firm. Contact him at 412-394-6690 or [email protected].
|This content has been archived. It is available through our partners, LexisNexis® and Bloomberg Law.
To view this content, please continue to their sites.
Not a Lexis Subscriber?
Subscribe Now
Not a Bloomberg Law Subscriber?
Subscribe Now
NOT FOR REPRINT
© 2024 ALM Global, LLC, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more information visit Asset & Logo Licensing.
You Might Like
View AllPa. Federal District Courts Reach Full Complement Following Latest Confirmation
The Defense Bar Is Feeling the Strain: Busy Med Mal Trial Schedules Might Be Phila.'s 'New Normal'
7 minute readFederal Judge Allows Elderly Woman's Consumer Protection Suit to Proceed Against Citizens Bank
5 minute readJudge Leaves Statute of Limitations Question in Injury Crash Suit for a Jury
4 minute readLaw Firms Mentioned
Trending Stories
- 1Call for Nominations: Elite Trial Lawyers 2025
- 2Senate Judiciary Dems Release Report on Supreme Court Ethics
- 3Senate Confirms Last 2 of Biden's California Judicial Nominees
- 4Morrison & Foerster Doles Out Year-End and Special Bonuses, Raises Base Compensation for Associates
- 5Tom Girardi to Surrender to Federal Authorities on Jan. 7
Who Got The Work
Michael G. Bongiorno, Andrew Scott Dulberg and Elizabeth E. Driscoll from Wilmer Cutler Pickering Hale and Dorr have stepped in to represent Symbotic Inc., an A.I.-enabled technology platform that focuses on increasing supply chain efficiency, and other defendants in a pending shareholder derivative lawsuit. The case, filed Oct. 2 in Massachusetts District Court by the Brown Law Firm on behalf of Stephen Austen, accuses certain officers and directors of misleading investors in regard to Symbotic's potential for margin growth by failing to disclose that the company was not equipped to timely deploy its systems or manage expenses through project delays. The case, assigned to U.S. District Judge Nathaniel M. Gorton, is 1:24-cv-12522, Austen v. Cohen et al.
Who Got The Work
Edmund Polubinski and Marie Killmond of Davis Polk & Wardwell have entered appearances for data platform software development company MongoDB and other defendants in a pending shareholder derivative lawsuit. The action, filed Oct. 7 in New York Southern District Court by the Brown Law Firm, accuses the company's directors and/or officers of falsely expressing confidence in the company’s restructuring of its sales incentive plan and downplaying the severity of decreases in its upfront commitments. The case is 1:24-cv-07594, Roy v. Ittycheria et al.
Who Got The Work
Amy O. Bruchs and Kurt F. Ellison of Michael Best & Friedrich have entered appearances for Epic Systems Corp. in a pending employment discrimination lawsuit. The suit was filed Sept. 7 in Wisconsin Western District Court by Levine Eisberner LLC and Siri & Glimstad on behalf of a project manager who claims that he was wrongfully terminated after applying for a religious exemption to the defendant's COVID-19 vaccine mandate. The case, assigned to U.S. Magistrate Judge Anita Marie Boor, is 3:24-cv-00630, Secker, Nathan v. Epic Systems Corporation.
Who Got The Work
David X. Sullivan, Thomas J. Finn and Gregory A. Hall from McCarter & English have entered appearances for Sunrun Installation Services in a pending civil rights lawsuit. The complaint was filed Sept. 4 in Connecticut District Court by attorney Robert M. Berke on behalf of former employee George Edward Steins, who was arrested and charged with employing an unregistered home improvement salesperson. The complaint alleges that had Sunrun informed the Connecticut Department of Consumer Protection that the plaintiff's employment had ended in 2017 and that he no longer held Sunrun's home improvement contractor license, he would not have been hit with charges, which were dismissed in May 2024. The case, assigned to U.S. District Judge Jeffrey A. Meyer, is 3:24-cv-01423, Steins v. Sunrun, Inc. et al.
Who Got The Work
Greenberg Traurig shareholder Joshua L. Raskin has entered an appearance for boohoo.com UK Ltd. in a pending patent infringement lawsuit. The suit, filed Sept. 3 in Texas Eastern District Court by Rozier Hardt McDonough on behalf of Alto Dynamics, asserts five patents related to an online shopping platform. The case, assigned to U.S. District Judge Rodney Gilstrap, is 2:24-cv-00719, Alto Dynamics, LLC v. boohoo.com UK Limited.
Featured Firms
Law Offices of Gary Martin Hays & Associates, P.C.
(470) 294-1674
Law Offices of Mark E. Salomone
(857) 444-6468
Smith & Hassler
(713) 739-1250