Dredging Company Denied $5.9M Indemnity Payout from US for Pipeline Rupture
A dredging company sued along with the U.S. government and ultimately hit with a nearly $14 million bench verdict for damaging an oil pipeline in…
November 01, 2017 at 03:40 PM
6 minute read
A dredging company sued along with the U.S. government and ultimately hit with a nearly $14 million bench verdict for damaging an oil pipeline in the Gulf of Mexico can't recover $5.9 million in indemnity from the government, a federal judge has ruled.
Weeks Marine paid out the entire $13.9 million judgment to Contango Operators Inc., a company it contracted with to build an underwater pipeline along with the U.S. Army Corps of Engineers. The government was found 60 percent negligent and Weeks 40 percent negligent for damage done to a Contango pipeline by a Weeks' vessel accidentally dredging over it.
The court ordered the government to reimburse Weeks $8 million for its share of the damages. Weeks subsequently sued the government for the remaining $5.9 million claiming the government negligently failed to inform it of the location of the pipeline.
However, U.S. District Judge Sim Lake of the Southern District of Texas wrote in his Oct. 31 opinion that Weeks mischaracterized a contractual claim as a negligence claim.
Citing a 2014 opinion in the case, Lake said, “Any claim that the USA was negligent for failing to inform Weeks Marine about the pipeline is essentially contractual. If the USA breached a duty by failing to include information in the contract, such a duty would be based in the contractual relationship, and a breach would have occurred by a failure to include the information in the contract.”
He continued, “Any claim that the USA was negligent for failing to inform Weeks Marine about the pipeline after the contract was signed similarly would involve a duty based in the contract — even if other duties might be implicated as well and a breach consisting of a failure to supply information that should have been included in the contract.”
As for whether Weeks was entitled to indemnity for any contractual claims, Lake found Weeks' arguments unconvincing.
Weeks argued that the the government's omission of the location of the pipeline in the contract was a positive assertion, or a representation on which it justifiably relied, and that the absence of the pipeline led to Contango's injuries.
“The omission of the pipeline by the Corps may have been a positive assertion and was one cause of Contango's injury,” Lake said, “but as the court previously held, Weeks Marine did not 'justifiably' rely on it. Weeks Marine possessed information about the Contango pipeline that it could have used to avoid striking the pipeline.”
Lake added, citing language from the 2014 opinion, “'Weeks Marine's sole reliance on information provided by the Corps did not satisfy its duty in this case to exercise reasonable care in its dredging operations.'”
Matthew F. Popp of Waits, Emmett & Popp in New Orleans represented Weeks and declined to comment. Peter G. Meyer of U.S. Department of Justice Civil Division represented the government and did not respond to a request for comment.
A dredging company sued along with the U.S. government and ultimately hit with a nearly $14 million bench verdict for damaging an oil pipeline in the Gulf of Mexico can't recover $5.9 million in indemnity from the government, a federal judge has ruled.
Weeks Marine paid out the entire $13.9 million judgment to Contango Operators Inc., a company it contracted with to build an underwater pipeline along with the U.S. Army Corps of Engineers. The government was found 60 percent negligent and Weeks 40 percent negligent for damage done to a Contango pipeline by a Weeks' vessel accidentally dredging over it.
The court ordered the government to reimburse Weeks $8 million for its share of the damages. Weeks subsequently sued the government for the remaining $5.9 million claiming the government negligently failed to inform it of the location of the pipeline.
However, U.S. District Judge
Citing a 2014 opinion in the case, Lake said, “Any claim that the USA was negligent for failing to inform Weeks Marine about the pipeline is essentially contractual. If the USA breached a duty by failing to include information in the contract, such a duty would be based in the contractual relationship, and a breach would have occurred by a failure to include the information in the contract.”
He continued, “Any claim that the USA was negligent for failing to inform Weeks Marine about the pipeline after the contract was signed similarly would involve a duty based in the contract — even if other duties might be implicated as well and a breach consisting of a failure to supply information that should have been included in the contract.”
As for whether Weeks was entitled to indemnity for any contractual claims, Lake found Weeks' arguments unconvincing.
Weeks argued that the the government's omission of the location of the pipeline in the contract was a positive assertion, or a representation on which it justifiably relied, and that the absence of the pipeline led to Contango's injuries.
“The omission of the pipeline by the Corps may have been a positive assertion and was one cause of Contango's injury,” Lake said, “but as the court previously held, Weeks Marine did not 'justifiably' rely on it. Weeks Marine possessed information about the Contango pipeline that it could have used to avoid striking the pipeline.”
Lake added, citing language from the 2014 opinion, “'Weeks Marine's sole reliance on information provided by the Corps did not satisfy its duty in this case to exercise reasonable care in its dredging operations.'”
Matthew F. Popp of Waits, Emmett & Popp in New Orleans represented Weeks and declined to comment. Peter G. Meyer of U.S. Department of Justice Civil Division represented the government and did not respond to a request for comment.
This content has been archived. It is available through our partners, LexisNexis® and Bloomberg Law.
To view this content, please continue to their sites.
Not a Lexis Subscriber?
Subscribe Now
Not a Bloomberg Law Subscriber?
Subscribe Now
NOT FOR REPRINT
© 2024 ALM Global, LLC, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more information visit Asset & Logo Licensing.
You Might Like
View AllBallast Water and Aquatic Invasive Species: The Unintended Consequences of Merchant Vessels
6 minute readBrewing Container Delay Disputes: When Will the Pandemic's Impact on Shipping Loosen Its Grip?
6 minute readTrending Stories
Who Got The Work
Michael G. Bongiorno, Andrew Scott Dulberg and Elizabeth E. Driscoll from Wilmer Cutler Pickering Hale and Dorr have stepped in to represent Symbotic Inc., an A.I.-enabled technology platform that focuses on increasing supply chain efficiency, and other defendants in a pending shareholder derivative lawsuit. The case, filed Oct. 2 in Massachusetts District Court by the Brown Law Firm on behalf of Stephen Austen, accuses certain officers and directors of misleading investors in regard to Symbotic's potential for margin growth by failing to disclose that the company was not equipped to timely deploy its systems or manage expenses through project delays. The case, assigned to U.S. District Judge Nathaniel M. Gorton, is 1:24-cv-12522, Austen v. Cohen et al.
Who Got The Work
Edmund Polubinski and Marie Killmond of Davis Polk & Wardwell have entered appearances for data platform software development company MongoDB and other defendants in a pending shareholder derivative lawsuit. The action, filed Oct. 7 in New York Southern District Court by the Brown Law Firm, accuses the company's directors and/or officers of falsely expressing confidence in the company’s restructuring of its sales incentive plan and downplaying the severity of decreases in its upfront commitments. The case is 1:24-cv-07594, Roy v. Ittycheria et al.
Who Got The Work
Amy O. Bruchs and Kurt F. Ellison of Michael Best & Friedrich have entered appearances for Epic Systems Corp. in a pending employment discrimination lawsuit. The suit was filed Sept. 7 in Wisconsin Western District Court by Levine Eisberner LLC and Siri & Glimstad on behalf of a project manager who claims that he was wrongfully terminated after applying for a religious exemption to the defendant's COVID-19 vaccine mandate. The case, assigned to U.S. Magistrate Judge Anita Marie Boor, is 3:24-cv-00630, Secker, Nathan v. Epic Systems Corporation.
Who Got The Work
David X. Sullivan, Thomas J. Finn and Gregory A. Hall from McCarter & English have entered appearances for Sunrun Installation Services in a pending civil rights lawsuit. The complaint was filed Sept. 4 in Connecticut District Court by attorney Robert M. Berke on behalf of former employee George Edward Steins, who was arrested and charged with employing an unregistered home improvement salesperson. The complaint alleges that had Sunrun informed the Connecticut Department of Consumer Protection that the plaintiff's employment had ended in 2017 and that he no longer held Sunrun's home improvement contractor license, he would not have been hit with charges, which were dismissed in May 2024. The case, assigned to U.S. District Judge Jeffrey A. Meyer, is 3:24-cv-01423, Steins v. Sunrun, Inc. et al.
Who Got The Work
Greenberg Traurig shareholder Joshua L. Raskin has entered an appearance for boohoo.com UK Ltd. in a pending patent infringement lawsuit. The suit, filed Sept. 3 in Texas Eastern District Court by Rozier Hardt McDonough on behalf of Alto Dynamics, asserts five patents related to an online shopping platform. The case, assigned to U.S. District Judge Rodney Gilstrap, is 2:24-cv-00719, Alto Dynamics, LLC v. boohoo.com UK Limited.
Featured Firms
Law Offices of Gary Martin Hays & Associates, P.C.
(470) 294-1674
Law Offices of Mark E. Salomone
(857) 444-6468
Smith & Hassler
(713) 739-1250